Astley Avenue watermain renewal

We are upgrading the Astley Avenue watermain to replace ageing assets and cater for future population growth

Start-finish: November 2018 – March 2019
Location: Astley Avenue, New Lynn
Status: Construction

Whats happening?

The pipeline along Astley Avenue, between Golf Road and Margan Avenue, is being replaced. The work will be undertaken in two stages between November 2018 and March 2019:

  • Phase 1 – Investigation and piloting of existing services – November 2018

  • Phase 2 – Watermain upgrade to be installed between December 2018 – March 2019

 
Traffic management will be in place – please follow instructions.

The route of the pipeline renewal. 

Any questions?

If you have any specific questions about this project, please contact;
Dave Moore, project manager
Phone: (09) 442 2222