Central Interceptor contractors' information

On 8 March 2018, Watercare announced the appointment of the short-listed construction contractors for the Central Interceptor project (in no particular order):

  • CPB Contractors
  • Ghella-Abergeldie Harker Joint Venture
  • Pacific Networks, comprising McConnell Dowell, Fletcher Construction and Obayashi
  • VINCI Joint Venture, comprising VINCI Construction Grands Projets, HEB Construction and Solentache Bachy.

The Request for Proposal will be released to the shortlisted respondents in May 2018. The contract is expected to be awarded in early 2019, with construction commencing in 2019 and to be completed in 2025.

Follow the links below for general information about the project.

Central Interceptor General Overview

CI geology long section

Media release (March 2018)

Should you wish to stay informed when new information becomes available, please register your interest by sending your details to CIproject@water.co.nz.