Clevedon water and wastewater network construction project

Clevedon village residents can now apply to connect to mains water and wastewater services.

Apply now for a Clevedon connection

Location: Clevedon
Status: Construction

Notice to residents

We currently have multiple projects underway in Clevedon as we work to finish the new water and wastewater network. Please keep an eye out for traffic management and follow directions to ensure the works can be completed as safely and quickly as possible. We are commencing work on new pipelines to allow water to reach our customers. Our team is working primarily on the berm and in the road shoulder. There will be some one-way lanes where the road narrows.

We are also actively working with our contractor and Auckland Transport to inspect each section of the current works area to ensure that reinstatement is up to standard and that the road is safe for road users. We are also working with Auckland Transport around a reseal programme for certain works that were put on hold pending the completion of our contract. The reseal programme is expected to take place over the summer months.
This week we have traffic management at:

  • 2 to 52 North Road
  • TMP (stop/go with traffic lights) at the corner of Clevedon/ Takanini Road and Burnside Road.

Project news

The main infrastructure construction project is complete with the central infrastructure now in place for water and wastewater services. Other key components to delivering services to homes and businesses are underway. We have two projects currently underway:

Dosing site project at 116 North Road

Status: In progress
Location: 116 North Road
Key outcome: To treat water as necessary until the network demand reaches higher levels
 

Local Water Reticulation Project

Status: In progress
Location: The first phase of this project is working from 1 North Road to 59 North Road and is expected to take 6 weeks from the beginning of July. Citycare then plans to move to Monument Road and Hyde Road. Further updates will be provided as the contractor progresses.
Key outcome: To enable existing residents and commercial sites to connect to the new water network. 

We are also undertaking testing of the main network and making fixes when necessary. There are some temporary works associated with this work which you will see around Clevedon. Check the Notice to Residents at the top of this page for details.

Apply for a connection in Clevedon

When can I connect? Click here to find out.
Click here for information on how to apply.


When launching new services there are a few key essentials that are required - demand for that service is important.

Eligible applications will be processed, and once fees have been paid they will be scheduled into our programme of works. As this is a wastewater vacuum designed solution, we will have contractors out in Clevedon installing the necessary wastewater vacuum pits for connections. The install of these pits will be co-ordinated by our project team. Water connections will also be scheduled.
 
Services will be made available from September; our Compliance Team will process final connections with your plumber from this date upon receipt of their network authorisation submission.

What are the benefits?

The networks will help address environmental pollution from failing septic tanks, provide reliable and safe water and wastewater services, as well as cater for growth in Clevedon.

Any questions?

If you have any specific questions about this project, please email [email protected] and one of our team will reply within three working days.

Newsletters

Clevedon Matters newsletter, July 2021