Dunkirk Road wastewater upgrades project

To cater for growth and reduce wastewater overflows into the Tamaki River.

Start-finish: June 2022 – late 2024
Location: Dunkirk Road, Panmure
Status: Construction
Button asking people to sign up for project updates

The project

Over the past 18 months, we have been working on the corner of Dunkirk Road and Tangaroa Street to construct a new pump station. We have also been working along Dunkirk Road installing a new gravity pipeline. This infrastructure will enable further development and service the growing population while reducing the risk of overflows into the Tāmaki River.

Stage 1 works

  • A new pump station on the corner of Tangaroa Street and Dunkirk Road. The increased capacity storage tanks and larger pumps will facilitate the storage of wastewater and reduce overflows during wet weather.

  • A new gravity main along Dunkirk Road from Tangaroa Street to Johnson Reserve. This is now complete.

Stage 2 works

  • A new rising main from the Dunkirk pump station to take flows on a more direct route to the Eastern Interceptor. This project will take place at a yet to be determined time.

The construction activities for Stage 1 works started mid-June and are now nearing completion. Currently, there are works happening in the pump station to complete the electrical switch room, making it watertight before installation of the electrical components. Additionally, the driveway hard stands, jib crane and davit arm will be installed within the next two months.

The jib crane is required for operational and maintenance purposes on the wet well and valve chamber. The pumps that will be installed in the wet well will weigh almost 1.5tonnes each, hence the need for a jib crane. This will be a permanent installation.

The jib crane height is 4.5-metres and has a swing radius of 5.2-metres. After listening to community concerns regarding the proposed yellow colour, it will now be rangoon green.
The jib crane at Dunkirk Road
Image: Jib crane
 

February 2024 update

Dunkirk Road open for full access from Monday 5 February

  • The only portion of the road that is closed and will remain that way until the completion of the project is between Tobruk and Tangaroa. This is to ensure the ongoing health and safety of both staff and community.

Coming up

  • Install the jib crane and davit arm at the pump station. This machinery will assist with maintenance and operational requirements. The davit arm is for safe access in and out of the wet well.

  • Connecting 31 private properties on the collector main within Dunkirk Road. This work will take place between Johnson Reserve and Tangaroa Street from June to August. This work may require a periodic single lane closure but will remain open for resident access.

  • Commissioning of the pump station will take place from April to June.

  • Landscaping around the MCC pump station (the new facility) will take place in July,

  • Demolition of the old pump station will take place in September and October.

  • We are expecting to demobilise out of the reserve by October. The hard fill will be removed and grass resown.

December 2023 update

  • Completed the laying of the gravity trunk sewer - 869 metres

  • Installed 46 manholes

  • Completed the manhole installation and pipe work within Johnson Reserve

  • Finished laying the collector main pipeline – 500 metres

  • Completed laying all 32 new house lateral connections

  • Installed 15 manholes

  • Completed the installation of the valve chamber, wet well and inlet manhole at the pump station

  • Commenced construction of the pump station control building

Dunkirk Fast Facts


Our work in pictures

In March, four 166,000 litre glass fibre-reinforced plastic storage tanks and four two-metre-wide maintenance holes were delivered to site. Before being lifted into place by crane, the team installed 160 sheet piles 14-metres underground and dug a further six metres to install the drainage and gravel bed for the tanks and manholes. So, how do the tanks work? Wastewater will be transported to them via a gravity main. The tanks will store wastewater until the network is ready for it to be pumped to a treatment plant. All this work will result in fewer wastewater overflows into the environment.

More information

If you would like to receive our newsletter, you can sign up by emailing [email protected].

Newsletters

Dunkirk wastewater upgrades newsletter August 2023
Dunkirk wastewater upgrades newsletter September 2022
Dunkirk wastewater upgrades newsletter February 2022

Any questions?

Please email: [email protected]

Image asking customers to tell us how they feel about our projects

Tell us how you really feel

We take our commitment to our customers seriously. We know that our infrastructure projects can at times be disruptive, so our team always tries their best to mitigate any potential issues and respond promptly to complaints. We want to make sure that we are continually improving how we deliver our projects to better benefit Auckland’s communities. Please let us know what we did well and where we can do better. Click the button below.

Button asking people to tell us how they feel about our projects