Howick watermain replacement project

To upgrade the water network to cater for growth in Pakuranga and the surrounding suburbs.

Start-finish: mid March – October 2023
Location: William Roberts Road
Status: Construction

Click here to sign up for project updates
 

What is the latest?

After a successful pipeline cutover (when the pipes are joined), the Howick loop main on William Roberts Road has been fully commissioned. This means that the existing watermain has now been replaced with the recently installed pipe. The next milestone will be on 19 October, when we switch to the new Bulk Supply Point (BSP) which will signal the end of the works. Our team endeavour to be out of the area a week after the completion of this connection. However, the Eastern Busway Alliance will continue upgrading and shifting our assets as their works progress.
 

About the project banner


Starting at the Pakuranga Road end of William Roberts Road and moving towards Ti Rakau Drive, the water pipe will be replaced in sections. We expect the pipe to replaced by October 2023. The Eastern Busway-William Roberts Road extension will be completed at the end of 2023, at which time crews will start works on the Reeves Road flyover.

How will the work affect you?

Road closures will be in place and vehicle access to properties may be impacted at times. If we need to restrict vehicle access to your property, you will be notified in advance.

Working hours

  • 7am to 6.30pm Monday to Friday and 7am to 2pm on Saturday including some public holidays. 

Traffic management and road closures

  • These will be in place throughout the works to keep the community and our team safe. Please follow the direction of site personnel and all site signage. 

Construction works

Temporary footpaths and road surfaces
Immediately after we complete the installation, these may not match the existing pavements. Please be assured that any surfaces which are temporarily filled will be returned to their original condition or better by the end of the project.

Any questions?

Please email us at: [email protected]

Image asking customers to tell us how they feel about our projects

Tell us how you really feel

We take our commitment to our customers seriously. We know that our infrastructure projects can at times be disruptive, so our team always tries their best to mitigate any potential issues and respond promptly to complaints. We want to make sure that we are continually improving how we deliver our projects to better benefit Auckland’s communities. Please let us know what we did well and where we can do better. Click the button below.