12 February 2024The latest on the repair
4pm Tuesday 13 February
Our crew have confirmed that the repair work has been completed and the watermain is currently recharging. You may already have low water pressure at your place, and full pressure is expected to return later this afternoon. If you experience discoloured water, run an outside tap for 5-10 minutes to flush the discolouration.
Break in the pipe at 699 Remuera Road
The new section of pipe can be seen in blue
Summary of the situation
Tuesday morning (13 February)
Our crews have been working to restore water to several streets in Remuera and Meadowbank after three pipe breaks within a 24-hour period.
First break: The initial break at Koraha Street was reported at 10am yesterday and repaired by 10pm.
Second break: The second break at 699 Remuera Road was reported at 4.30pm yesterday and repaired by 11:30pm.
Third break: The third break at 699 Remuera Road was discovered at 2am this morning and the repairs are ongoing. We have customer liaising staff onsite.