Herne Bay collector tunnel
A project aimed at delivering cleaner beaches on the Waitematā Harbour by 2028.
Duration
2025 - 2028
Location
Herne Bay
Status
Planning
Project overview
In combination with Watercare’s new Central Interceptor tunnel, the Herne Bay collector tunnel will collect combined wastewater and stormwater overflows for safe treatment at Māngere Wastewater Treatment Plant. This new infrastructure will significantly reduce overflows into the environment and improve the quality of our swimmable beaches.
Italian tunnelling company, Ghella, is continuing early works as we progress towards signing the final contract, when a Construction Programme will be finalised.
We will construct a 2.1m-diameter tunnel for approximately 1.5km using a micro Tunnel Boring Machine (mTBM). The pipeline will pass beneath the streets at depths ranging from 9-22 metres.
We will also:
- Install eight tunnel shafts, along with intercepting shafts connections to existing engineered overflow points (EOPs), which are manholes in the roadway or on private property.
- Install small diameter pipelines along Marine Parade (600mm in diameter) and local connections to the existing engineering overflow points (between 200mm to 450mm in diameter). These will be constructed using open trenching to lay pipes.
- Establish two temporary Construction Support Areas (CSAs): one at Salisbury Reserve and the other in the area beside the Curran Street motorway on-ramp.
The map below shows the location of the proposed works.

Click here to see the full size map
Main tunnelling and shaft site works
Early works contractor, Ghella, has completed service investigations across the project area. Over the next few months, we will carry out service relocations in preparation for the main Herne Bay Collector construction.
There will be three construction sites in the Sarsfield/Wallace/Argyle Street area, all located in the roadway at intersections. Service relocations are currently scheduled to from early January until April. All sites are fenced to keep everyone safe while we establish the area and put in a raised working platform. The sites will then be set up for a longer period of main construction works (shaft excavation and tunnelling) with altered traffic management plans put in place.
Site safety and traffic management
All our work sites are fenced off with hoardings for the safety of the passing public and our workforce. Traffic management may include stop/go controls or single lanes and areas of no parking, as and when temporary road closures are needed.
We will aim to reduce the impact to road users as much as possible and alternative routes around our sites will be available. You will always have access to your property. Please work with and obey all traffic signs and directions for everyone’s safety.
Areas affected by traffic management plans

Point Erin Park: South-west corner works
We are making good progress planning for the Point Erin Park south-west corner works (control chamber and plant room), which will integrate with the main Herne Bay tunnel (HBT) project.
Now that service investigations have been completed, we will relocate services in preparation for site establishment. Power cables and some streetlights will be relocated on Curran and Sarsfield Streets. In the southwest corner of the park itself, we will relocate fibre and communication lines as well as wastewater and water pipes.
The image below shows the location of the shaft and the control chamber.

Salisbury Reserve temporary storage facility
Salisbury Reserve has been consented for use by the Herne Bay tunnel project as a temporary storage facility.
St Marys Bay and Herne Bay separation projects
These projects were earlier works that focused on separating the old, combined stormwater and wastewater pipes.
Herne Bay collector tunnel consent documents
Herne Bay collector tunnel consent documents
Consent Lodgement - July 2023
1 Herne Bay Trunk sewer AEE pdf
Appendix A Permitted Activities pdf
Appendix B Proposed Conditions pdf
Appendix C Records of Title pdf
Appendix D1 Geotechnical Assessment pdf
Appendix F Integrated Traffic Assessment pdf
Appendix G Arboricultural Assessment pdf
Appendix H Archaeological Assessment pdf
Appendix I General Arrangement Drawings pdf
Appendix J Construction Methodology pdf
Appendix K1 Noise and Vibration Assessment pdf
Updated Consent Lodgement - August 2023
Methodology Cover Letter - 8 August 2023
s92 Updated Herne Bay Trunk Sewer Assessment of Environmental Effects - 7 August 2023 v3
s92 Proposed Conditions - 7 August 2023
Construction Methodology - 8 August 2023
Draft of Construction Noise & Vibration Management Plan - 3 August 2023 v1
Construction Noise & Vibration Assessment - 3 August 2023 v1
s92 Response & Updated Documentation - October 2023
Resource Consent Application - s92 Request - 1 September 2023
s92 Response Letter - 5 October 2023
Attachment A: Groundwater & Settlement Assessment Report - September 2023 v4
Attachment B1: Erosion & Sediment Control- Site Plan - 22 September 2023 v2
Attachment B2: Draft Erosion & Sediment Control Plan Report - 22 September 2023 v2
Attachment C: Construction Noise & Vibration Technical Assessment - August 2023 v1
Attachment D: Construction Noise & Vibration Management Plan - September 2023 v1.1
Attachment E1: CSA-1 Concept Layout Plan
Attachment E2: CSA-2 Concept Layout Plan
Attachment G: Arboricultural Assessment of Effects - 9 June 2023
Attachment H: Proposed Salisbury Reserve Reinstatement Concept Sketch - 7 September 2023
Attachment I: Approved Reserve Reinstatement Plan 94a - 94b Shelly Beach Road - 23 March 2021
Attachment J: Street Tree Replanting Memo & Plans - 7 September 2023
Herne Bay Trunk Sewer: Amendments To Application - 13 October 2023
s92 Further Information Responses - November - December 2023
Hearing Evidence
Hearing Evidence of Andrew Clarke (Structural Engineering) - 2 February 2024
Hearing Evidence of Andrew Deutschle (Corporate) - 2 February 2024
Hearing Evidence of Colin Shields (Transport) - 2 February 2024
Hearing Evidence of Jeremy Elley-Brown and William Hung (Consultation) - 2 February 2024
Hearing Evidence of Julia Wick (Landscape and Visual) - 2 February 2024
Hearing Evidence of Maree Drury (Planning) - 2 February 2024
Hearing Evidence of Mark Thomas (Geotechnical) - 2 February 2024
Hearing Evidence of Rory Bishop (Construction Methodology) - 2 February 2024
Hearing Evidence of Sean McBride (Arboricultural) - 2 February 2024
Hearing Evidence of Sharon Yung (Noise and Vibration) - 2 February 2024
Hearing Evidence of Stephen Webster (Corporate) - 2 February 2024
Hearing Evidence Drawings
2. Longitudinal Section - Trunk Sewer.pdf
3. Longitudinal Section - Local Network Sheet 1.pdf
4. Longitudinal Section - Local Network Sheet 2.pdf
5. Longitudinal Section - Local Network Sheet 3.pdf
6. Longitudinal Section - Local Network Sheet 4.pdf
7. Construction Plan - Tunnel Shaft Locations.pdf
8. Construction Plan - Interception Shaft Locations.pdf
9. Land Requirement Plan (CSA1).pdf
10. Land Requirement Plan (CSA2).pdf
11. Street Tree Replanting Plan.pdf
12. Salisbury Reserve Plan (CSA1) as per Appendix 2 of the evidence of Julia Wick.pdf