Nihotupu 1 watermain upgrade
A watermain replacement project to renew aging infrastructure in the Titirangi area.
Duration
May 2025 - approximately mid-2026
Location
Titirangi and Glen Eden
Status
Construction
Project overview
The original Nihotupu 1 watermain was laid around 1905 from cast-iron pipe. Water is pumped from the Titirangi Reservoirs to the Nihotupu Reservoir and supplies approximately 18,000 elevated customers in Laingholm and Titirangi.
Due to the age and condition of the existing Nihotupu 1 watermain it needs to be replaced improve reliability for the future.
Most construction activity has been focused in the Titirangi area, with additional works in Glen Eden.
Please refer to the overall site map to show the extent of the entire project.

Update on current works in the area
Atkinson Road, Titirangi
Our watermain works on Atkinson Road are now nearing completion, and we’re also building an additional pump station as part of the Nihotupu 1 project. This will help strengthen the local water network and improve reliability.
- We expect to finish works on Atkinson Road by Wednesday 5 February 2026 including reinstating the road and surrounding area.
- Our goal is to have road reinstatement completed before school returns in February 2026, where possible.
Rosier Road, Solar Road, and Pisces Road (Glen Eden)
Watermain works are complete and connection works are underway. These are scheduled to be finished by early February 2026.
Kaurilands Road, Titirangi
These works are complete. Please note there are some minor works for approximately two days in the footpath outside 58 Kaurilands Road in January 2026.
Daffodil Street and Konini Road, Titirangi
Our watermain works on these streets are now complete.
Scenic Drive and Huia Road, Titirangi
Watermain works are now complete. Please note we will need to carry out connections early in the new year and the final reinstatement of the trench on Huia Road.
Upcoming works in Glen Eden – Withers Road, Kashmir Road, and Nandana Drive
While working in the area we have also identified additional sections of the local water network in Glen Eden that require upgrading. These areas include Withers Road, Kashmir Road, and Nandana Drive.
By laying this additional watermain now, we can complete the work more efficiently and avoid the need to return at a later date.
- These works are expected to begin in February 2026
- The work is expected to take approximately four months
Remaining connection works in nearby locations
There are still a small number of connections to be completed in nearby areas, including:
- Scenic Drive
- Rosier Road
Please refer to the map below for the works area

How will this impact you?
- Working hours will be from 8pm to 5am Monday to Sunday for our night works on Scenic Drive and Huia Road. Working hours for our other sections of work will be from 7am to 6.30pm, Monday to Friday and 7am to 4pm on Saturday including some Statutory Holidays.
- Working hours for other sections of work will generally be 7am to 6.30pm, Monday to Friday, and 7am to 4pm on Saturdays, including some statutory holidays where required.
- Traffic management will be in place in the form of a stop-go operation during our night shifts.
- Some street parking will need to be temporarily removed near the work site to allow traffic management to be setup as part of the approved traffic management plan.
- Construction will generate some noise and vibration; however, levels will be kept to a minimum and in accordance with Auckland Council and consent requirements.
- Water supply to properties will not be affected during these works.