I'm a

Whenuapai and Redhills wastewater project

Wastewater upgrades are required to cater for development.

Duration

Early 2024 - late 2027

Location

Whenuapai, Redhills and Hobsonville

Status

Construction

Get regular updates

Project overview

The Whenuapai Redhills Wastewater Scheme is a key component of Watercare's wastewater investment programme supporting growth across Northwest Auckland.

The project will provide wastewater capacity to support existing communities and future urban development within Whenuapai, Red Hills, Hobsonville and surrounding growth areas.

Package 3 has now been completed. The project is now progressing into the delivery of a merged construction programme incorporating Packages 1 and 2.


The proposal

The merged Package 1 and 2 programme includes:

Package 1

  • Interim Pump Station (IPS)
  • Associated wastewater rising mains
  • Open trench and trenchless pipeline construction
  • Chambers and network connections
  • Utility relocations and protection works
  • Decommissioning of the Whenuapai Village Pump Station

Package 2

  • Break Pressure Tank (BPT) at Mamari Road
  • Massey Connector Tunnel
  • Northern Interceptor Tunnel Phase 2
  • Shafts 8, 12, 14 and 17
  • Hobsonville Pump Station connection
  • Air Treatment Facility and odour control systems
  • Mechanical, electrical and control infrastructure

The project includes approximately 3.8km of wastewater tunnels, associated shafts, pumping infrastructure and pipeline connections extending between Whenuapai, Red Hills and Hobsonville.


Timeline

Package 1: October 2027 - February 2030

Package 2: December 2026 - February 2030

Package 3: Completed


Project map

Whenuapai and Redhills overall project map

Current works

Package 3 Completion

Works associated with Package 3 have now been completed, including the construction of new wastewater pipelines and associated reinstatement activities.


Upcoming Works - Package 1 & 2

Preparations are underway for the commencement of the merged Package 1 and 2 construction programme, which will deliver major wastewater infrastructure across Whenuapai and Hobsonville.

Early activities will include site establishment, stakeholder engagement, detailed construction planning, utility coordination and enabling works ahead of main construction.

Residents, landowners, businesses and stakeholders will receive further information prior to works commencing in their area.


Consent documents

Consent decisions and approved plans
Package 1 Revised Regional Consent Lodgement and S92 Appendices- November 2023
Package 1 Revised NoR Lodgement - October 2023
Package 2 Lodged Consent Application Documents
Package 1 Original Regional Consent and NoR Lodgement - October 2022
Package 1 NoR S92 Request & Responses - November 2023 - March 2024
Package 1 Regional Consent S92 Request & Responses - January 2024 - February 2025

Package 1 Regional Consent S92 Request & Responses - January 2024 - February 2025

Get in touch